Projects

Old 41 Widening

Old 41 widening hero

Project Name

Old 41 Widening

Location

Lowndes County, Georgia

Owner

Lowndes County Board of Commissioners

Project Details

The year-long widening project undertaken for the Lowndes County Board of Commissioners (BOC) involved various essential components to enhance the infrastructure. The project encompassed clearing the right-of-way (ROW), as well as implementing stormwater management systems, water infrastructure, base construction, curb and gutter installation, and the application of asphalt.

To facilitate effective stormwater management, 6,579 linear feet of storm pipe were installed as part of the project. Additionally, a substantial amount of 16,135 tons of granite-graded aggregate base (GAB) and 18,650 tons of asphalt were utilized to ensure the durability and smoothness of the road surface.

The project also required significant earthwork, with approximately 31,572 cubic yards of dirt being moved to accommodate the widening process. Furthermore, a total length of 11,032 linear feet of curb and gutter was constructed to enhance drainage and delineation along the roadway.

Undertaking such a comprehensive project showcases The Scruggs Company’s commitment to improving transportation infrastructure and accommodating the growing needs of the community. By investing in critical elements like stormwater management, base construction, and curb and gutter installation, the project aims to provide a safer and more efficient road network.

The successful completion of this year-long widening project will undoubtedly have a positive impact on the mobility and accessibility for both residents and visitors in Lowndes County.

Services Provided

  • Asphalt Paving & Construction
  • Stormwater Drainage
  • Grading & Earthwork
  • Curb & Gutter

Services Provided

  • Asphalt Paving & Construction
  • Stormwater Drainage
  • Grading & Earthwork
  • Curb & Gutter

Project Details

The year-long widening project undertaken for the Lowndes County Board of Commissioners (BOC) involved various essential components to enhance the infrastructure. The project encompassed clearing the right-of-way (ROW), as well as implementing stormwater management systems, water infrastructure, base construction, curb and gutter installation, and the application of asphalt.

To facilitate effective stormwater management, 6,579 linear feet of storm pipe were installed as part of the project. Additionally, a substantial amount of 16,135 tons of granite-graded aggregate base (GAB) and 18,650 tons of asphalt were utilized to ensure the durability and smoothness of the road surface.

The project also required significant earthwork, with approximately 31,572 cubic yards of dirt being moved to accommodate the widening process. Furthermore, a total length of 11,032 linear feet of curb and gutter was constructed to enhance drainage and delineation along the roadway.

Undertaking such a comprehensive project showcases The Scruggs Company’s commitment to improving transportation infrastructure and accommodating the growing needs of the community. By investing in critical elements like stormwater management, base construction, and curb and gutter installation, the project aims to provide a safer and more efficient road network.

The successful completion of this year-long widening project will undoubtedly have a positive impact on the mobility and accessibility for both residents and visitors in Lowndes County.